«SLIABH LIAG An appraisal of the current footpath management project on the mountain Dr. Bob Aitken Summary 1. Introduction: Mountaineering Ireland ...»

-- [ Page 1 ] --

SLIABH LIAG

An appraisal of the current footpath management project on the mountain

Dr. Bob Aitken

Summary

1. Introduction: Mountaineering Ireland invited me to visit Sliabh Liag to offer advice on the current

path repair project and its execution. I have 30 years of upland footpath management experience in

Scotland and other parts of the world.

2. Site visit: I spent a full day on Sliabh Liag on 16 September with representatives from Mountain Ireland, from Donegal County Council, and from the contractor managing the current project. We inspected and discussed the full length of the works under contract.

3. Site appraisal: Sliabh Liag is inherently unsuitable as a location for the development of a tourist path by virtue of its rugged character, length, and environmental sensitivity, not least as a Natura site.

Even for repair and construction to hill path standards it presents awkwardly varied and technically very challenging topographical and ecological conditions, including at least three very difficult sites.

4. The project: the conception of the project as a single-push ‘solution’ for the whole length of this difficult path was excessively ambitious, given the scale and technical challenges of the site, but also because the path diagnostic skills, specification practice, and technical ability needed for quality upland path repair and reconstruction are still developing in Ireland.

5. The specification for the path works: the engineering-based specification for the work appears excessively prescriptive and inflexible for upland path work, not least in face of the markedly varied site conditions on Sliabh Liag. The criteria for path alignment are unclear; the techniques specified seem heavy-handed and restricted when less constructional, less technically demanding, and less expensive methods could have sufficed on long runs of the path. Prescriptions in respect of key elements such as drainage, path definition, and re-use of spoil are inadequate.

6. Execution of the works: the contractor clearly had limited insight into the problems posed by conditions on Sliabh Liag, and there was little evidence that he was ready to take the steps necessary to address those problems. His workers appeared to have minimal relevant experience, with little understanding of the problems they were dealing with and the technical skills needed. The work was advancing in a piecemeal fashion, with key problem sites not yet addressed. There was considerable variation from the specification. Significant hazard to walkers was evident, from loose stones in pitching and from mobile stones laid into peat. The stone being used in flagstone pitching was well below specification, and as laid offered no prospect of stability even in the short term. The current disposal of spoil risks significant damage to the natural vegetation of the site.

7. Overview: the current works undertaken on the path are almost certain to be ineffective because of problems of alignment, inappropriate techniques, sub-standard materials, and weak execution due to wholly inadequate levels of skill and experience. It seems very doubtful that the volume of work outstanding can be completed to appropriate standards within contract. A substantial re-structuring of the work would seem to be the only mechanism by which the situation can be remedied.

8. Recommendations:

Set aside the current full-path programme and focus on selected key sites.

Apply the specification selectively and flexibly to deal with the priority sites.

Reinforce the contract team urgently to strengthen its ability to delivery safe and sustainable works, by bringing in additional skills and experience in supervision, training and execution.

–  –  –

An appraisal of the current footpath management project on the mountain

1. Introduction Mountaineering Ireland (MI) invited me at short notice to visit Sliabh Liag and to offer advice on the current path repair project and its execution. My background experience in path management is summarised at Annex 2. I had not previously been on the hill, though I had visited the carpark once some years ago in atrocious weather. MI supplied me with notes and photographs from earlier site visits in the development of the project and during the current works, but I had limited opportunity to read and digest the specification document before seeing the site.

2. Site visit I visited the mountain on 16 September with Helen Lawless and Dennis Golden for MI; Aidan McGrenra of Donegal County Council (DCC) and Jeremy Smith, advisor to the Council. Paul Duffy of Metro contractors and his assistant joined us at the outset, but after early discussions they distanced themselves from most of our detailed debate, and had left the site some time before we had a final review discussion at the carpark. We spent about 8 hours on the path in total.

We walked out and back over the whole part of the route to Sliabh Liag for which works are proposed.

Conditions were exceptionally dry. This is a large site, complex in its range of topography and ground conditions, which really needs two or three visits for a full diagnostic understanding. In particular I would have liked to see it in wetter conditions to assess the patterns of drainage and the state of the ground on the deep-peat sections.





Despite the fine weather the number of walkers on the path beyond the viewpoint was quite limited, probably less than thirty or forty over the day, a good proportion being European visitors.

3. Site appraisal: the nature of the mountain and its path In my view Sliabh Liag is inherently unsuitable as a location for the development of a tourist path for general visitors. The site is marked by an abrupt transition from the roadend to the rugged cliff top, with its up-and-down crest line and its bounding abrupt drop over the cliffs. It is a good distance along the ridge to the main top of the mountain, making for a considerable walk whether out-and-back or as a circuit via the Pilgrim Route. For visitors not looking for a mountain walk nor accustomed to this kind of wild landscape, it may well feel a somewhat threatening place in any but the finest weather. These attributes may be reflected in the present pattern of use, with only 5% of 160,000 users reportedly venturing beyond the viewpoint area within about 200 metres from the carpark. The first fairly steep and broken initial slope is a useful filter to separate committed walkers from casual visitors.

From a footpath management perspective, this is also a path with awkwardly varied topography and ecology, from apparently dry and reasonably fertile grassy swards on shallow soils on broad open ridges in its earlier stages to difficult sites with deep peat on steep slopes and over steeply shelving bedrock slabs. Deep peat on open slopes of moderate-to-steep gradients presents technical challenges to which no very satisfactory light-touch solutions have yet been found. Some of the sites lie on or immediately behind narrow crests. Even for very experienced path managers and workers, these sites would present considerable technical and safety challenges to achieve a sustainable low-key route to hill path standards for committed walkers.

But to construct a safe, stable and durable footpath for general tourist visitors in these circumstances would need a highly constructional intervention that would cause a radical transformation in the essential nature and quality of the mountain environment, particularly given its Natura designation.

2 Given these difficult site characteristics, an iterative approach to path management would have seemed advisable, to explore issues of path alignment, visitor containment and direction, and repair or construction techniques in a progressive programme, probably over several years. That might have begun with light intervention along the path to fix or forestall problems, or with a focus on key defining sections or acutely difficult damaged sites. I would suggest there are at least three acute sites where this kind of

iterative work could usefully have been focused, two of them having significant safety implications:

 the traverse around the knoll at the Eagle’s Nest, where the current path runs round an open corner across an exposed and degrading slope close above the cliff edge.

 the ascent towards the long dome of Shanbally, particularly on the first sharp rise from the col and on the steep upper slope, where it would be advantageous to cut off the current long leftwards traverses to the ridge above the cliff slope. Those traverses have been broken down by trampling into highly conspicuous lines of damage. Both these sites have steep deep peat over boulders.

 the traverse of the lower crest knoll at Keeringear, where the crest line is narrow, airy, rocky and awkward, but the backslope traverse runs on very steep broken peat over sharply dipping rock slabs, and has already seen one substantial slump.

Work was under way on the first two of these sites, but with likely problematic outcomes, as discussed below.

4. The project Given the challenging scale and difficulty of the Sliabh Liag path, the undertaking of the project as a substantial and ambitious capital programme with a tight timetable has induced its own problems, not least the expectation of a total solution for the full length of the path. In my view this was an overly ambitious objective. The problem was only compounded by the delivery at an early stage of large volumes of stone by helicopter along the path to sites where constructional techniques were yet to be proven.

It is quite understandable that the office who specified the works, the project manager, and subsequently the contractor, lacked a full understanding of upland path process or a firm grasp of the difficult issues along the path. Given the distinctively problematic environmental conditions found on Irish hills, and the currently developing state in Ireland of path diagnostic skills, specification practice, and technical ability needed for quality upland path repair and reconstruction, it would perhaps have been more judicious to proceed by increments along the path, or as mentioned above, to trial and develop solutions for key sites first. The appropriate metaphor would be trying to run before one can walk.

5. The specification for the works The specification for the path works is a substantial piece of work. However I feel its approach is illadapted to the nature of the task on Sliabh Liag. It may have drawn for techniques and standards on footpath management manuals, some of them developed for application in different environments, but it is essentially modelled on engineering practice. I would suggest that that style is excessively prescriptive and inflexible for upland path work, not least in face of the marked variation in site conditions on Sliabh Liag.

While the objectives of the project may possibly be found clearly stated in other documents, they are not explicit in the specification. As a result it is difficult to identify what criteria determined the selected path alignment, the desired path standard and style, or the techniques to be used. From discussion on the ground it appeared that there was an intention to provide a path appropriate to bring tourist visitors up to higher viewpoints on the first section of the path, but not to encourage them beyond that point. Given that premise; the techniques specified for the path as a whole seem heavy-handed and restricted in range and response to site conditions, when less heavily constructional, less technically demanding, and less expensive solutions might well have sufficed on long runs of the path.

–  –  –

The specification demonstrates a lack of in-depth experience and diagnostic understanding of physical processes on mountain paths, and of the range of path construction and repair techniques. Some of the techniques recommended for general application, especially the strong emphasis on stone construction either as ‘blockstone pitching’ or as ‘flagging’ seem inappropriate for significant parts of the path. At low grades and especially on the earlier parts of the path, a geotextile-based gravel path over peat sections could have been quicker and easier to build than either of the rock-based techniques. The specification’s prescriptions in respect of key technical areas like drainage, path definition, and the re-use of spoil are weak if not flawed.

Though its prescriptions and statements of technical standard were sometimes very precise, I would have to say that the works specified were not always necessary, or not as uniformly required as the specification suggested. Work on Sliabh Liag demonstrates the inherent conflict between the need for a detailed specification on the one hand, and the need on the other for a degree of flexibility in response to the problems posed by unforeseen and sometimes unforeseeable site conditions.

For the sake of brevity here, I have outlined a number of more detailed technical points on the specification in Annex 1, with some related comments on execution.

6. Execution of the works The contractor clearly had limited insight into the problems posed by conditions on Sliabh Liag. More problematically, there was limited evidence that he was ready to take the steps necessary to address those problems when identified. The work was advancing in a piecemeal fashion, with key problem sites not yet addressed. There was considerable variation from the specification in size of stone being used, in packing base layers of rock into peat, in drainage works, and in the disposal of spoil.

The contractor’s workers, though willing, appeared to have minimal relevant experience, with little understanding of the challenges they were dealing with and the technical skills needed. This was especially true in their execution of ‘blockstone’ pitching, acknowledged as a demanding technique, where the results lacked basic stability and often produced awkward and uncomfortable walking surface.



Pages:   || 2 |


Similar works:

«        APPENDIX L SOLAR GLARE HAZARD ANALYSIS   THIS PAGE INTENTIONALLY LEFT BLANK. Seville Solar Farm Complex: Solar Glare Hazard Analysis Date: November 20, 2014 To: Dwight Carey From: Josh Proudfoot, Aaron Toneys and Justin Overdevest Key Findings Fixed-tilt photovoltaic (PV) arrays do present glare issues to the residences due west of the • project site for short intervals (15-30 minutes) of potential after-image glare at sunrise in nonwinter months (mid-March through October). The...»

«Dr. Architect Dafna Fisher Gewirtzman Jan 2011 RESUME Dafna Fisher Gewirtzman Marital Status: Married to Raanan Gewirtzman and the mother of Tomer (20) and Ella (8) Home Address: 21 Camille Huismans, Haifa, Israel Tel: +972-4-8258780 Cell: +972-54-7833331 Fax: +972-4-8245748 Email: ardafna@tx.technion.ac.il ACADEMIC DEGREES 1999 Ph.D. Faculty of Architecture and Town Planning at the Technion-Israel Institute of Technology. 1993 Master of Science in Architecture, Cum-Laude Technion-Israel...»

«REASSESSING THE NEGLIGENCE STANDARD OF CARE FOR MINORS CAROLINE FORELL* Most American jurisdictions have two different standards of care, the adult reasonable person under the circumstances standard and the more individualized child standard of care for situations where the negligence of a minor causes injuries.' Courts and commentators claim that the adult standard is used when a minor was engaged in an adult activity.2 An analysis of the cases involving the use of firearms and motor vehicles...»

«FOR SALE: BEAUTIFUL FAMILY HOME, 3 BEDROOMS, FRIENDLY POLTERGEIST AND UNIQUE REPUTATION AS LOCAL MURDER SITE — THE OBLIGATIONS OF DISCLOSURE ON REAL ESTATE AGENTS UNDER THE FAIR TRADING ACT (NZ)/TRADE PRACTICES ACT (CTH). DEBRA WILSON I. INTRODUCTION The doctrine of caveat emptor1 requires a prospective purchaser to satisfy himself as to the quality of the property he is considering purchasing. There is therefore no obligation on the vendor to reveal any information about the property, and...»

«Land Change Science Program Social Values for Ecosystem Services, Version 3.0 (SolVES 3.0)—Documentation and User Manual Open-File Report 2015–1008 U.S. Department of the Interior U.S. Geological Survey U.S. Department of the Interior SALLY JEWELL, Secretary U.S. Geological Survey Suzette M. Kimball, Acting Director U.S. Geological Survey, Reston, Virginia: 2015 For more information on the USGS—the Federal source for science about the Earth, its natural and living resources, natural...»

«Berk, R.A. (2011). How to create “Thriller” PowerPoints® in the classroom! Innovative Higher Education, 37(2). DOI: 10.1007/s10755-011-9192-xOnline First™ (http://www.springerlink.com/content/l1r176516kr26p12/) (Journal publisher will not allow me to post PDF on my Web. Online version is available now using link provided; hard copy will be available in April 2012. I’m sorry for the inconvenience.) How to Create “Thriller” PowerPoints® in the Classroom! Ronald A. Berk Abstract:...»

«Tomorrow Land The Call might Tomorrow Land accomplish from their paper but will make to prove your information by all financial infrastructure following in few retirees. The epub if difficult banners are to be an accessibility expected out in their access. Very, see the offense if your everyone but months. Have Tomorrow Land important where you have the corner amongst you permanently actually download of those hours live presenting to make papers for their growth. Not through a words and...»

«AFTER LIBERATION HUMAN CAME DESTRUCTION RIGHTS WATCH Iraqi Militias and the Aftermath of Amerli After Liberation Came Destruction Iraqi Militias and the Aftermath of Amerli Copyright © 2015 Human Rights Watch All rights reserved. Printed in the United States of America ISBN: 978-1-6231-32354 Cover design by Rafael Jimenez Human Rights Watch defends the rights of people worldwide. We scrupulously investigate abuses, expose the facts widely, and pressure those with power to respect rights and...»

«The Fellowship of Solitude Small Group/Devotional Guide Finding balance amid the hustle and bustle of life and its many calls to interactive community     “Immediately Jesus made the disciples get into the boat and go on ahead of him to the other side, while he dismissed the crowd. After he had dismissed them, he went up on a mountainside by himself to pray. When evening came, he was there alone.” —Matthew 14:22-23         ©2012 Bruce Heydt 1 “Through the call of Jesus men...»

«425 OECD/OCDE Adopted: 17th December 2001 OECD GUIDELINE FOR TESTING OF CHEMICALS Acute Oral Toxicity – Up-and-Down Procedure INTRODUCTION 1. OECD guidelines for the Testing of Chemicals are periodically reviewed in the light of scientific progress or changing assessment practices. The concept of the up-and-down testing approach was first described by Dixon and Mood (1)(2)(3)(4). In 1985, Bruce proposed to use an up-and-down procedure (UDP) for the determination of acute toxicity of chemicals...»

«Gleanings g Alberta Council Trefoil Guilds Annual Newsletter Jan 2014 Edition Published by Girl Guides of Canada, Alberta Council 11055 107 Street, Edmonton AB Excerpts from a letter to the local paper by T5H 2Z6 Sheryl Paquette of 3rd Parkland, Silver Willow (780) 424-5510 Guild, on the occasion of: e-mail info@albertagirlguides.com Website: www.albertagirlguides.com 100th Anniversary of Girl Guides in Alberta Alberta Trefoil Guild Adviser: Gail Armstrong As a long time member of the...»

«Miles, M. 2007-08. “Disability and Deafness in East Asia: Social and Educational Responses, from Antiquity to Recent Times. A bibliography of European-language materials with introduction and some annotation.” (This work revises and greatly extends an earlier bibliography on the former History of Education website at the Catholic University of Nijmegen). Internet publication URLs: http://independentliving.org/docs7/miles200708.html and http://independentliving.org/docs7/miles200708.pdf The...»





 
<<  HOME   |    CONTACTS
2016 www.dissertation.xlibx.info - Dissertations, online materials

Materials of this site are available for review, all rights belong to their respective owners.
If you do not agree with the fact that your material is placed on this site, please, email us, we will within 1-2 business days delete him.