WWW.DISSERTATION.XLIBX.INFO
FREE ELECTRONIC LIBRARY - Dissertations, online materials
 
<< HOME
CONTACTS



«EIA FOR THREE 10MW PHOTOVOLTAIC (SOLAR) ENERGY FACILITIES PROPOSED FOR MARIENTAL, OMARURU AND OKAHANDJA BACKROUND INFORMATION DOCUMENT PURPOSE OF ...»

EIA for three proposed 10 MW photovoltaic (solar) energy facilities at Mariental, Omaruru and Okahandja, Namibia

EIA FOR THREE 10MW PHOTOVOLTAIC

(SOLAR) ENERGY FACILITIES

PROPOSED FOR MARIENTAL, OMARURU

AND OKAHANDJA

BACKROUND INFORMATION DOCUMENT

PURPOSE OF THIS DOCUMENT

The purpose of this Background Information Document (BID) is to provide stakeholders with a background to three proposed solar energy facilities and to invite Interested and Affected Parties (I&APs) to register in the Environmental Impact Assessment (EIA) process. By registering as an I&AP, stakeholders can submit comments on the proposed solar energy facilities and be kept informed throughout the EIA. This BID includes the following

sections:

 Introduction  How does the EIA Process work?

 What is Public Participation and how do you get involved?

 What is proposed and where?

 Why are solar energy facilities needed and what benefits are anticipated?

 How does a typical solar energy facility work?

 What alternatives are being considered?

 Potential environmental impacts associated with the project  Way forward Introduction Namibia Power Corporation (Pty) Ltd (NamPower) propose to off-take power from an Independent Power Producer (IPP) or Producers (IPP’s). The power will be generated from three individual 10 megawatt (MW) photovoltaic (PV) solar energy facilities at three separate locations in Namibia namely; Mariental, Omaruru and Okahandja (Figure 3).

In terms of the Namibian environmental legislation (Environmental Management Act (No. 7 of 2007)), an EIA is required to obtain an Environmental Clearance Certificate from the Ministry of Environment and Tourism (MET) before the project can proceed. As a preferred IPP or IPP’s has not yet been selected, NamPower has appointed Aurecon South Africa (Pty) Ltd (Aurecon) to undertake the EIA study to investigate the biophysical and socio- economic environmental issues. The findings will help inform MET’s decision-making and to inform the design and operation of the three proposed PV solar energy facilities.

HOW DOES THE EIA PROCESS WORK?

An EIA is a process that evaluates the biophysical and socio-economic characteristics of proposed projects and the consequences of the project on the environment and the people that live in the area affected by the project activities.

Where negative impacts are likely to result from the project, measures can be recommended to avoid or lessen these impacts to a level where the impacts are considered acceptable from a biophysical and social perspective. Where positive impacts are likely to result from the project, measures can be recommended to increase these impacts. The EIA process also provides I&APs with opportunities to comment on the project and to be kept informed about decisions that may impact on them or the environment. The various stages of the consultation within the EIA process are shownin Figure 2.

–  –  –

Figure 1 | Locality Map indicating the project locations The EIA process would typically consist of a scoping phase and an EIA phase. However, MET’s decision can be informed by the scoping report if sufficient information is provided at this stage. Due to the impacts of solar energy facilities being well understood, the scoping report will include specialist assessments of the proposed project, assessments of all anticipated impacts and mitigation measures to address the anticipated impacts which should be sufficient for decision making by MET.It is therefore anticipated that the project would not need to proceed to the EIA phase.

–  –  –

Okahandja) and on the Aurecon website (www.aurecongroup.com) and the NamPower website (www.nampower.com.na)  Registered I&APs will also be informed of the availability of the Draft Scoping Report for a 14 day comment period, during which period the public will have the opportunity to review the draft document and raise any issues or concerns  Advertising the decision received from MET and affording an opportunity to I&APs to appeal the decision.

WHAT IS PROPOSED AND WHERE?

NamPower identified three existing substations into which each of the proposed solar energy facilities could feed, based on the grid capacity, network of existing transmission lines, the national map of solar radiation indicating the average sunshine hours per day and location of the largest source of demand. The three substations identified were the Hardap substation near Mariental, Omburu substation near Omaruru and Osona substation near Okahandja.

Three alternative sites, were identified at each substation and assessed by specialists. Each alternative site is approximately 100 hectare (ha) in extent and within a 5km radius from the substation. All sites are located on farming land, which are currently used for stock grazing, transmission line corridors and are uninhabited. A site selection process was undertaken to select the preferred three sites (one alternative site per substation location). The site selection process will be detailed in the Scoping Report. It should be noted that Osona site 1 was decreased in size as a small hill, considered to be sensitive in a number of aspects, was distorting the findings for the site and hence was excluded from the original 100 ha site for the site selection process. The following sites were selected as the





preferred sites (see Figure 3, Figure 4 and Figure 5):

 Hardap site 1 on Farm Koichas 89 close to Mariental, Hardap Region (referred to as Hardap site);

 Omburu site 3 located on Omaruru Townlands Portion B, 2215 close to Omaruru, Erongo Region (referred to as Omaruru site); and  Osona site 1 located on Portion C of Farm Gross Barmen 7 near Okahandja, Otjozondjupa Region (referred to as Osona site).

An area of 35ha is generally required to construct a 10MW PV solar energy facility. Areas with a footprint of 35ha were therefore identified within the 100ha sites, informed by sensitive features on site, which were excluded from the development area.

Each of the proposed 10MW solar energy facilities would consist of the following:

 Photovoltaic component: numerous rows of PV panels and associated support infrastructure to generate electricity.

 Transmission corridor: one overhead 66kV transmission line located within the transmission corridor to connect the proposed onsite substation to the existing main substation.

 On-site substation: the on-site substation to collect the electricity produced on site and step it up to the correct voltage to transfer via the transmission line to the existing main central substation.

 Access road corridor: a 100m corridor to accommodate the access road for constructing, servicing and maintaining the facility.

 Buildings: operation and maintenance buildings to house equipment and a guard cabin for security.

 Additional infrastructure: includes a boundary fence for health, safety and security reasons; water supply infrastructure for groundwater abstraction and storm water infrastructure, if required.

WHY ARE SOLAR ENERGY FACILITIES NEEDED AND WHAT BENEFITS ARE

ANTICIPATED?

Namibia has a high reliance on power imports (on average 60%, but up to 80 % during dry seasons). A number of Namibia`s energy import agreements are about to end and if not renewed, Namibia is likely to face a capacity deficit in its electricity generation from 2015.

–  –  –

This is based on current growth forecasts of its electricity demands (peak demand of 534MW with a 4% per annum growth)1. In order to address the potential capacity deficit, and to take advantage of the good solar resource in Namibia, NamPower is proposing to purchase electricity from solar energy facilities.

Renewable energy is recognised internationally as a major contributor in diminishing the negative effects of climate change, as well as providing a wide range of biophysical environmental, economic and social benefits that can contribute towards long-term global sustainability. These impacts include, amongst others, reduction of greenhouses gases emitted per unit of electricity, reduced reliance on fossil fuelled power stations, employment benefits and associated social upliftments, improvement in electricity security and diversity, and expenditure in local economy.

The proposed solar energy facilities are therefore expected to contribute positively towards climate change mitigation. The establishment of the proposed solar energy facilities would also help to meet the current national electricity demand, which far exceeds supply. Furthermore, the proposed projects would assist Namibia in meeting its international obligations by aligning domestic policy with internationally agreed strategies and standards as set by the Kyoto Protocol and United Nations Convention on Biological Diversity, to which Namibia is a signatory.

HOW DOES A TYPICAL PV SOLAR ENERGY FACILITY WORK?

Solar panels capture light energy from the sun to generate electricity through a process known as the PV effect, where light energy energise the electrons to produce electricity (see Figure 62). There are various types of solar panels, but for the proposed PV solar energy facilities Conventional PV solar cells are proposed.

–  –  –

WHAT ALTERNATIVES ARE BEING CONSIDERED?

The best suitable site at each location (Mariental, Omaruru and Okahandja) was selected through the Multi-criteria Decision-Making process. This is therefore forms the assessment of alternatives and only the preferred site location alternative will be assessed in detail against the “no-go” option in the assessment phase. Mounting alternatives and access road alternatives will however be considered in the EIA process. For all three sites, two mounting alternatives

to fasten the panel to the frame will be considered, namely:

a) Single-Axis Tracking PV: The panels are fixed on a a b single axis that follows the seasonal sun to ensure maximum exposure to sunlight as indicated in in Figure 7a.

b) Fixed Tilt PV: This is typically a rack mounted system of panel arrays on frames and installed at a fixed angle (see Figure 7b). These arrays would be uniformly aligned to facilitate efficient sun energy capture. Figure 7 | Mounting Alternatives 1 UNDP Environmental Finance Services, July 2011. Concentrating Solar Power Technology Transfer for Electricity Generation in Namibia, (CSP TT) NAM.

2 Figure 5 Source: NamPower

–  –  –

The following access road alternatives, as indicated in Figure 2, Figure 4 and Figure 5 will be considered:

 Hardap: two access road alternatives will be considered with Alternative 1 following the existing farm road running north-west of the substation. Alternative 2 follows the existing access road to the substation that would be extended to the proposed site.

 Omburu: one access road alternative following the existing transmission service road to provide direct access to the main road.

 Osona: two access road alternatives will be considered with Alternative 1 being a new access road to connect the proposed PV to the main road via the shortest distance. Alternative 2 follows the existing substation access road.

POTENTIAL ENVIRONMENTAL IMPACTS ASSOCIATED WITH THE PROJECTS

–  –  –

WAY FORWARD Further work will be done to compile the Draft Scoping Report. Following the completion of the Draft Scoping Report, it will be lodged in the respective libraries (Mariental, Omaruru and Okahandja), on the Aurecon website as well as the NamPower website. Registered I&APs will be notified of the lodging and given an opportunity to comment on the report. Should you wish to raise any initial issues or concerns regarding the proposed projects, or if you wish to register as an I&AP, please contact the Public Participation Office at the details below.

–  –  –

Background Information Document Page 9



Similar works:

«The Program Thursday Evening, February 4, 2016, at 8:30 The Songs of Todd Almond With special guests Courtney Love, Sherie Rene Scott, and Brandon Victor Dixon Lear deBessonet, Director David Bloom, Musical Director Barrie McLain, Vocals Sylver Wallace, Vocals Angela Sclafani, Kate Douglas, Molly McAdoo, Sirens Bobby Lewis Ensemble Josh Henderson and Sarah Goldfeather, Violin Sarah Elizabeth Haines, Viola Eric Allen, Cello Jon Spurney, Piano and Guitar Ann Klein, Guitar Jeremy Chatzky, Bass...»

«Journal of Assembly 1 December 2 JOURNALS of the LEGISLATIVE ASSEMBLY of the PROVINCE OF NEW BRUNSWICK SECOND SESSION OF THE FIFTY-FIFTH LEGISLATIVE ASSEMBLY, 2004-2005 THE HONOURABLE HERMÉNÉGILDE CHIASSON LIEUTENANT-GOVERNOR Fredericton, N.B. Thursday, December 2, 2004. PROCLAMATION WHEREAS I have proclaimed that the first session of the fiftyfifth Legislative Assembly of this Province be prorogued on the second day of December, 2004, in the forenoon; AND WHEREAS I have thought fit to call...»

«Included in this download are the answers to some fan questions. Make sure to check out the corresponding non-spoiler sheet – there is different information on there. Past sheets are available on my website: http://clstonebooks.com/goodies-and-giveaways/ Don’t tell Mr. Blackbourne! ♥ C. L. Warning – spoilers ahead!1. Are we going to learn how Lily and her team got together? A. Yes. It’s a planned series but it isn’t going to come around until probably Scarab Beetle’s story ends....»

«Gleanings Columbia District United Methodist Women June 2014 Columbia District 42nd Annual Meeting Theme: September 20, 2014 Union United Methodist Church 7582 Woodrow Street Irmo, SC 29063 (803) 781-3013 What’s Coming Up. June 17 Registration:  Columbia District Executive 8:15AM – 9:00AM Committee MeetingUnion UMC, Irmo, SC Program: July  9:00AM Rural Mission, Inc. Special Emphasis Month Keynote Speaker: July 24-26  Rev. Mallory Forte Mission u – Spartanburg Methodist College,...»

«References Albarracin-Jordan, Juan V.1992. Prehispanic and early Colonial settlement patterns in the Lower Tiwanaku Valley, Bolivia. Unpublished Ph.D. dissertation, Department of Anthropology, Southern Methodist University. Ann Arbor: University Microfilms.1996. Tiwanku: Arqueologia regional y dinamica segmentaria. La Paz: Plural editores.. Albarracin-Jordan, Juan V., and James Edward Mathews 1990. Asentamientos prehispanicos del valle de Tiwanaku Vol. 1. La Paz: Producciones Cima. Alconini...»

«Fazendo Gênero 9 Diásporas, Diversidades, Deslocamentos 23 a 26 de agosto de 2010 O FILHO DA MÃE, DE BERNARDO CARVALHO: ROTAS ENTRE O ESPAÇO E O CORPO Adenize Franco Algumas proposições Com fragmentos tais foi que escorei minhas ruínas/ Pois então vos conforto. (T. S. Eliot, A terra desolada) A produção literária de Bernardo Carvalho inscreve-o dentro da lista dos principais autores da atualidade. Reconhecido por romances como Nove Noites e Mongólia, o autor é nomeado, segundo...»

«Haunted Canada: The Ninth Annual Trent-Carleton 2013 Graduate Conference in Canadian Studies. Held at Carleton University, March 15-16 Text of “Haunting to Heal: The Poetry of Duncan Mercredi,” by Michael Minor. Cree poet Duncan Mercredi is haunted by the memory of his ancestors, but it is a haunting that he welcomes and even fosters. In a response to the gothic tradition of representing Aboriginal people and their spiritual practices as something to be repressed, Mercredi asserts the power...»

«Contents Transportation 5 Places of Interest 6 Amphoe Mueang Udon Thani 6 Amphoe Ban Phue 11 Amphoe Na Yung 14 Amphoe Nong Han 14 Amphoe Ban Dung 17 Amphoe Kumphawapi 17 Amphoe Nong Saeng 17 Amphoe Wang Sam Mo 18 Amphoe Kut Chap 20 Events and Festivals 20 Local Products and Souvenirs 21 Souvenir Shops 21 Tour Operators 22 Rental Car Companies 23 Interesting Activities 23 Golf Courses 23 Tours Programmes 23 Facilities in Udon Thani 24 Accommodations 24 Restaurants 27 Vegetarian Restaurants 29...»

«Obituary Zafar ishaq ansari (December 27,1932–april 24, 2016) Glimpses in memOriam Muzaffar Iqbal “Allah keeps as His friend one who has three characteristics: generosity like that of a river, from which whosoever desires can drink; warm affection like that of the sun, which illuminates every place; and humility like that of the earth, which permits both the good and the wicked to live on it.” This saying of Muʿīn al-Dīn Chishtī (1141-1236), the founder of the eponymous sufi order in...»

«University System of Maryland Council of University System Staff (CUSS) Fall 2009 Report to USM Institutions Bowie State University 14000 Jericho Park Road Bowie, MD 20715 Coppin State University 2500 W. North Avenue Baltimore, MD 21216 Frostburg State University 101 Braddock Road Frequently Asked Questions Regarding Frostburg, MD 21532 Salisbury University FY2010 Budget Cuts, Furlough and 1101 Camden Avenue Salisbury, MD 21801 Temporary Salary Reductions Towson University 8000 York Road...»

«ACTA ENTOMOLOGICA MUSEI NATIONALIS PRAGAE Published 30.vi.2010 Volume 50(1), pp. 157–166 ISSN 0374-1036 A review of Ripiphoridae in the Arabian Peninsula (Coleoptera: Tenebrionoidea) Jan BATELKA Nad Vodovodem 16, CZ-100 00 Praha 10, Czech Republic; e-mail: janbat@centrum.cz Abstract. Distribution of the Ripiphoridae (Coleoptera: Tenebrionoidea) in the Arabian Peninsula is evaluated. Six species belonging to the genera Macrosiagon Hentz, 1830 and Ripiphorus Bosc, 1791 are figured and keyed,...»

«PAPER TRB03-3410 Synthesis on the Safety of Right Turn on Red in the United States and Canada Dominique Lord Center for Transportation Safety* Texas Transportation Institute Texas A&M University System 3135 TAMU College Station, TX 77843-3135 Tel. (979) 458-1218 Fax. (979) 845-4872 E-mail: d-lord@tamu.edu Web: http:\\tti.tamu.edu November 2002 Paper presented at the 82nd Annual Meeting of the Transportation Research Board *This study was performed before the author joined the Texas...»





 
<<  HOME   |    CONTACTS
2016 www.dissertation.xlibx.info - Dissertations, online materials

Materials of this site are available for review, all rights belong to their respective owners.
If you do not agree with the fact that your material is placed on this site, please, email us, we will within 1-2 business days delete him.